Completed
Pipeline extension
Approved
Wote Water Supply Project Phase I
Makueni · Makueni · Makueni
Overall Progress
100.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Wote Water Supply
Start Date
09 Feb 2020
Planned End
09 Mar 2021
Actual End
09 Mar 2023
Contractor
Lafey Construction Company Limited
Consultant
-
Location Type
Urban
Target Areas
Wote Town
Kwa Nzilu
Kwa Thuvi
Scope of Works
• Water Reticulation Network Line 2, Line 3 and Line 4
• Kwa Nzuili to Kwa Thuvi pipeline(Proposed Water Kiosk Point),
• Rehabilitation of the Kamunyolo Treatment Plant,
• Rehabilitation of Kamunyolo-Makueni Boys Rising Main
• Construction of 100m3 Elevated Steel Tank, 12m high at Kamunyolo
• Construction of 5No. Water kiosks with 5m3 plastic tanks on top
Impacts
The project serve 9,750 residents (2200 households) of Kwa Thuvi, Muambani and Kwa Francis Mutuku within Wote Town with clean, reliable and adequate water supply
Key Challenges
The project was given a one year extension due to delay in exchequer release
Remarks
The project is complete, operational, and has been handed over to the County Government of Makueni
GPS Coordinates
37.62058, -1.77637
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 55.0M
Total
KES 55.0M
Beneficiaries
1,950
Households
9,750
Population
Technical Specs
Volume Abstracted
2,000.00 m³/day
Treatment Capacity
2,000.00 m³/day
Storage Reservoir
150.00 m³
Treated Water Mains
4.00 km
Distribution Lines
15.00 km
Water Kiosks
5
Connections
400
Created 16 Aug 2026, 14:46
· Last updated 16 Aug 2026, 17:18