Completed
Pipeline extension
Approved
Mavoko Water and Sewer Interventions Extension of Pipeline Phase II & III
Machakos · Mavoko · Makadara, Athi River West
Overall Progress
100.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Mavoko Water Supply
Start Date
07 Jan 2022
Planned End
01 Jan 2024
Actual End
01 Jan 2024
Contractor
Invegus Limited
Consultant
-
Location Type
Urban
Target Areas
Ngei
KMC
Athi River
Scope of Works
• 27.8 Km of various sizes water supply pipelines including fittings
• 1.8 Km sewer lines
• Manholes and valve chamber
• Construction of 250 m3 elevated steel tank
• Consumer Connection kits
• Capacity building for MAVWASCO
Impacts
The project serve 3,500 households with clean, safe, and affordable water
Key Challenges
The project was delayed due to delayed exchequer release
Remarks
The project is complete, operational, and has been handed over to Mavoko Water and Sanitation Company
GPS Coordinates
36.98591, -1.449935
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 173.0M
Total
KES 173.0M
Beneficiaries
1,240
Households
6,200
Population
Technical Specs
Volume Abstracted
2,500.00 m³/day
Treatment Capacity
12,000.00 m³/day
Storage Reservoir
250.00 m³
Treated Water Mains
7.80 km
Distribution Lines
20.00 km
Water Kiosks
4
Connections
250
Created 16 Aug 2026, 14:46
· Last updated 16 Aug 2026, 17:18