Completed
Borehole
Approved
Dr. Likimani/Kyang’ombe primary school water project
Kajiado · Kajiado East · Kitengela
Overall Progress
100.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Water for Schools
Start Date
07 Aug 2022
Planned End
10 Jun 2022
Actual End
01 Apr 2023
Contractor
All-Fzaan Investment Limited
Consultant
-
Location Type
Rural
Target Areas
School
Scope of Works
• Drilling and Equipping of borehole
• Distribution for the school
• Water Storage tank for the school
Impacts
The project serves the target area with clean, safe, and affordable water
Key Challenges
The project was delayed due to delayed exchequer release
Remarks
The project is complete, operational, and has been handed over to the community
GPS Coordinates
36.97367, -1.47781
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 8.0M
Total
KES 8.0M
Beneficiaries
260
Households
1,300
Population
Technical Specs
Volume Abstracted
150.00 m³/day
Treatment Capacity
150.00 m³/day
Storage Reservoir
20.00 m³
Treated Water Mains
0.20 km
Distribution Lines
0.80 km
Water Kiosks
1
Connections
1