Ongoing
Spring
Approved
Isinet Water Supply project
Kajiado · Kajiado South · Mbirikani/Eselenkei
Overall Progress
2.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Isinet Water Supply
Start Date
06 Jan 2025
Planned End
-
Actual End
-
Contractor
-
Consultant
-
Location Type
Rural
Target Areas
Isinet community
Public institutions
Scope of Works
• Rehabilitation of 1No.spring source at Enkongu spring.
• Solarisation of Nabulaa A borehole
• Replacing 6km of DN 90mm HDPE from Enkongu spring to Isinet
• Construction of 5km DN 63mm HDPE pipeline to Endikir.
• Construction of 2No.community water point and cattle trough at Duka Moja and Endikirr.
Impacts
(i) upon completion will serve 3,260 people (650 households)
(ii) Will employ 12 people during construction
(iii) Will permanently employ 4No. Of operators during operation phase
Key Challenges
Lack of funds to commences the construction works even though the detailed designs are ready
Remarks
(i)Final designs complete
(ii) EIA complete
GPS Coordinates
37.533339, -2.533610
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
652
Households
3,260
Population
Technical Specs
Volume Abstracted
826.00 m³/day
Storage Reservoir
450.00 m³
Distribution Lines
11.00 km
Water Kiosks
2
Connections
2
Created 16 Aug 2026, 14:46