Ongoing
Water Supply
Approved
Kilgoris Water Supply and Sanitation Project
Narok · Kilgoris · Kilgoris and Lolgorian
Overall Progress
92.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Start Date
01 Apr 2021
Planned End
01 Apr 2023
Actual End
-
Contractor
China State Construction Engineering Company Ltd
Consultant
GIBB Africa
Location Type
Rural Urban
Target Areas
Kilgoris, Lolgorian and environs
Scope of Works
Water distribution network and rehabilitation of existing system
To benefit over 40,000 people
Impacts
Improve access to water
Key Challenges
Wayleave acquisition
Remarks
The Project is currently 92% complete and preparation for commissioning is ongoing.
GPS Coordinates
-1.0071, 34.8813
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 51.6M
Adb
🌍 Foreign
· Loan
KES 516.2M
Total
KES 567.8M
Beneficiaries
8,200
Households
41,000
Population
Technical Specs
Volume Abstracted
2,000.00 m³/day
Treatment Capacity
2.00 m³/day
Storage Reservoir
900.00 m³
Treated Water Mains
43.50 km
Distribution Lines
43.50 km
Water Kiosks
5
Created 16 Aug 2026, 15:10
· Last updated 16 Aug 2026, 17:18