Ongoing
Borehole
Approved
Londopua Borehole
Turkana · Turkana South · Lobokat/Kainuk
Overall Progress
40.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Equalization Fund Project Phase ll
Start Date
07 Mar 2024
Planned End
10 Mar 2024
Actual End
-
Contractor
Darglobe Company Limited
Consultant
-
Location Type
Rural
Target Areas
Lodoupua and Kakong area
Scope of Works
Drilling, Equipping and Civil Works with elevated tower
Impacts
Improve access to water
Key Challenges
Borehole dry
Remarks
Drilling of site 1No complete with borehole reported dry
GPS Coordinates
2.048239, 35.52934
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 9.7M
Total
KES 9.7M
Beneficiaries
1,200
Households
6,000
Population
Technical Specs
Storage Reservoir
24.00 m³
Water Kiosks
1
Created 16 Aug 2026, 15:10
· Last updated 16 Aug 2026, 17:18