Report Back to Projects
Completed Water Supply Approved

Naisoya Pri. School Borehole water project

Narok · Narok North · Narok

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Start Date
05 Sep 2024
Planned End
08 Oct 2024
Actual End
08 Oct 2024
Contractor
Brookes Contracting Limited
Consultant
-
Location Type
Rural
Target Areas
Naisoya Pri. School Borehole water project
Scope of Works
Construction of 3No Water Kiosks, 4.6km pipeline extension and rehabilitation of 2No Water Kiosk
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Works complete and operational
GPS Coordinates
-0.930027, 35.860020
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 4.9M
Total KES 4.9M
Beneficiaries
400
Households
3,500
Population
Technical Specs
Volume Abstracted 50.00 m³/day
Storage Reservoir 50.00 m³
Water Kiosks 5