Completed
Borehole
Approved
Nganoini ECD Karunga sec school Borehole
Nyandarua · Gilgil · Murindat
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Start Date
-
Planned End
-
Actual End
-
Contractor
Balimond Solutions Ltd
Consultant
-
Location Type
Rural
Target Areas
Nganoini ECD Karunga sec school Borehole
Scope of Works
Equipping of the borehole
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Project is complete and operational
GPS Coordinates
-0.408941, 36.360071
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 4.9M
Total
KES 4.9M
Beneficiaries
360
Households
2,450
Population
Technical Specs
Volume Abstracted
160.00 m³/day
Storage Reservoir
20.00 m³
Water Kiosks
1
Created 16 Aug 2026, 15:10
· Last updated 16 Aug 2026, 17:18