Completed Water Pan Approved

Tangulbei Water Pan

Baringo · Tiaty East · Tangulbei

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
GoK Directly Funded Projects
Start Date
04 Oct 2024
Planned End
04 Apr 2025
Actual End
04 Apr 2025
Contractor
-
Consultant
-
Location Type
Rural
Target Areas
Tangulbei Water Pan
Scope of Works
Construction of 18,0000m3 water pan
Impacts
Improve access to water
Key Challenges
No challenges
Remarks
Project 100% complete.
GPS Coordinates
0.8000327306298592, 36.27782946325791
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 9.1M
Total KES 9.1M
Beneficiaries
400
Households
2,000
Population
Technical Specs
Storage Reservoir 18,000.00 m³