Completed
Water Supply
Approved
Relocation of Ihwagi Intake
Nyeri · Mathira · Iriani
Overall Progress
100.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Water Harvesting Programme
Start Date
06 Jun 2023
Planned End
06 Jul 2024
Actual End
-
Contractor
Sori Investment Ltd
Consultant
-
Location Type
Rural
Target Areas
Karatina Town and its Environs
Scope of Works
Construction of new intake and inlet chamber
Laying of raw water gravity mainline
Construction of 10m3 Break Pressure Tank (BPT)
Impacts
The project has facilitated farming activity within the area.
Key Challenges
Late GOK disbursement and contactor citing financial constrains.
Remarks
Improving access to safe water for domestic use.
GPS Coordinates
36.633361110,0.633361110
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 42.9M
Total
KES 42.9M
Beneficiaries
800
Households
4,000
Population
Technical Specs
Volume Abstracted
2,800.00 m³/day
Storage Reservoir
10.00 m³
Distribution Lines
9.20 km