Ongoing
Borehole
Approved
Kimbimbi Sub- County Hospital
Kirinyaga · Mwea · Nyangati
Overall Progress
63.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Universal Health Coverage
Start Date
02 Sep 2021
Planned End
-
Actual End
-
Contractor
Octagon Builders & General Suppliers
Consultant
-
Location Type
Urban
Target Areas
Kimbimbi Hospital
Scope of Works
Connect to Mwea Makima Water system 2.5km away;
Erection of 50m3; Pressed Steel Elevated Tank;
Improvement of rain water harvesting facilities
Impacts
Provision of safe water
Key Challenges
GOK late disbursments . Contractor citing financial constraints
Remarks
Need for Improved Coordination and Timely Funding
GPS Coordinates
-0.619696590,37.370918850
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 7.1M
Total
KES 7.1M
Beneficiaries
1
Households
500
Population
Technical Specs
Volume Abstracted
36.00 m³/day
Storage Reservoir
50.00 m³
Distribution Lines
2.50 km
Created 16 Aug 2026, 15:50