Ongoing
Water Supply Project
Approved
Ngariama Njukiini Water Supply Project
Kirinyaga · Gichugu · Ngariama
Overall Progress
23.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Drought Intervention/Mitigation Program
Start Date
-
Planned End
-
Actual End
-
Contractor
Alwahab Enterprises Ltd
Consultant
-
Location Type
Rural
Target Areas
Gichugu
Scope of Works
Construction of 1 no. Cross weir and an intake chamber.
Laying DN 280 mm – 6.36 km long raw water gravity main
Treatment works capacity 4,200m3 per day
DN 450/315/280/225mm –
Treated Water Gravity Mains
DN 160-110mm-8.5 km
distribution pipelines.
1 No. -225m3 Clear Water Tank at the Treatment Works. Rehabilitation of 3No. Ground
Masonry Tanks.
Impacts
Provision of safe water
Key Challenges
GOK late disbursments . Contractor citing financial constraints
Remarks
Need for Improved Coordination and Timely Funding
GPS Coordinates
321.000000000,321.000000000
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 268.1M
Total
KES 268.1M
Beneficiaries
14,000
Households
70,000
Population
Technical Specs
Volume Abstracted
4,200.00 m³/day
Treatment Capacity
4,200.00 m³/day
Storage Reservoir
225.00 m³
Treated Water Mains
6.36 km
Distribution Lines
8.50 km