Report Back to Projects
Ongoing Water Supply Project Approved

Ngariama Njukiini Water Supply Project

Kirinyaga · Gichugu · Ngariama

Overall Progress
23.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Drought Intervention/Mitigation Program
Start Date
-
Planned End
-
Actual End
-
Contractor
Alwahab Enterprises Ltd
Consultant
-
Location Type
Rural
Target Areas
Gichugu
Scope of Works
 Construction of 1 no. Cross weir and an intake chamber.  Laying DN 280 mm – 6.36 km long raw water gravity main  Treatment works capacity 4,200m3 per day  DN 450/315/280/225mm – Treated Water Gravity Mains  DN 160-110mm-8.5 km distribution pipelines.  1 No. -225m3 Clear Water Tank at the Treatment Works. Rehabilitation of 3No. Ground Masonry Tanks.
Impacts
Provision of safe water
Key Challenges
GOK late disbursments . Contractor citing financial constraints
Remarks
Need for Improved Coordination and Timely Funding
GPS Coordinates
321.000000000,321.000000000
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 268.1M
Total KES 268.1M
Beneficiaries
14,000
Households
70,000
Population
Technical Specs
Volume Abstracted 4,200.00 m³/day
Treatment Capacity 4,200.00 m³/day
Storage Reservoir 225.00 m³
Treated Water Mains 6.36 km
Distribution Lines 8.50 km
Created 16 Aug 2026, 15:50 · Last updated 16 Aug 2026, 17:18
County Overview
Loading…
Loading…

Fetching entity performance details…