Completed
Borehole
Approved
Kasafari Borehole
Embu · Runyenjes · Gaturi North
Overall Progress
100.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Cross-County Programme
Start Date
-
Planned End
02 Jun 2021
Actual End
-
Contractor
Octagon Builders and General Supplies Central Water Company Limited
Consultant
-
Location Type
Rural
Target Areas
Kasafari Community
Scope of Works
Drilling, development, test pumping and equipping with solar powered pumping system
Borehole drilled to 256m depth - 8m3/h yield obtained
Impacts
Improves access to clean water AND create employment opportunities
Key Challenges
Late disbursement of government funds.
Remarks
Need for Improved Coordination and Timely Funding
GPS Coordinates
9945820.000000000,354648.000000000
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 4.9M
Total
KES 4.9M
Beneficiaries
60
Households
300
Population
Technical Specs
Volume Abstracted
64.00 m³/day
Storage Reservoir
24.00 m³
Water Kiosks
1
Created 16 Aug 2026, 15:50