Ongoing
Borehole
Approved
Kamigua Primary School Borehole
Embu · Mbeere North · Nthawa
Overall Progress
0.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Water for Schools
Start Date
-
Planned End
-
Actual End
-
Contractor
Instapump
Consultant
-
Location Type
Rural
Target Areas
Kamigua Primary School
Scope of Works
Drilling, development and test pumping
Impacts
Improves access to clean water and create employment opportunities
Key Challenges
Non-performance and contractor's failure to resume and complete works
Remarks
Awaiting Equipping
GPS Coordinates
9942039.000000000,367186.000000000
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 1.5M
Total
KES 1.5M
Beneficiaries
1
Households
300
Population
Technical Specs
Storage Reservoir
24.00 m³
Water Kiosks
1
Created 16 Aug 2026, 15:50