Report Back to Projects
Completed Borehole Approved

Nakwemikwi Kopeto Water Supply Project

Turkana · Turkana Central · Lodwar Township

Overall Progress
100.00%
Project Overview
Implementing Agency
North Rift Valley Water Works Developmnet Agency
Programme
Drought Intervention/Mitigation Program
Start Date
-
Planned End
-
Actual End
-
Contractor
Hydrotech Associates Ltd
Consultant
-
Location Type
Rural
Target Areas
Lodwar Municipality, Naipa center, dispensary and Kopeto Primary school
Scope of Works
Rehabilitation, solarization and hybrid system of the 3No. Boreholes
Impacts
Increased supply to residents for better quality life and lower energy cost to the operator
Key Challenges
High demand versus low supply and high maintainace cost
Remarks
Complete & operational
GPS Coordinates
3.05'43.32''N 35.33'33.39E
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 9.0M
Total KES 9.0M
Beneficiaries
1,500
Households
5,000
Population
Technical Specs
Volume Abstracted 200.00 m³/day
Storage Reservoir 150.00 m³
Distribution Lines 3.00 km
Water Kiosks 4
Connections 200
Created 16 Aug 2026, 15:51 · Last updated 16 Aug 2026, 17:18
County Overview