Ongoing
Water Supply
Approved
Mois Bridge Matunda Water Supply Project
Uasin Gishu, Kakamega & Trans Nzoia · Soy, Cherangany & Lukuyani · Moi's Bridge
Overall Progress
5.00%
Project Overview
Implementing Agency
North Rift Valley Water Works Developmnet Agency
Programme
North Rift Valley WWDA Projects
Start Date
-
Planned End
-
Actual End
-
Contractor
Blue Swift Contractors and General Supplies Limited
Consultant
Professional Consultants in association with Kagga and partners
Location Type
-
Target Areas
Mois Bridge and Matunda
Scope of Works
Construction of the Intake weir on Chepkaitit River
Laying of Raw Water Mains Nominal Diameter 400m
Construction of Water Treatment Works with a daily production capacity of 14,270m3/day
Laying of 73.9km transmission pipelines in sizes ranging from nominal diameter 315-110
Laying of 105.3km distribution pipelines in sizes ranging from nominal diameter 200-50
Construction of 2no. masonry storage tanks & rehabilitation of 6no. masonry tanks total capacity 1,550m3
Construction of 1500m3 and 500m3 concrete tanks at Maji mazuri and Milimani
Construction of 11no. water kiosks
Impacts
NIL
Key Challenges
NIL
Remarks
The contractor has mobilized to site and prepared access roads to both intake and Treatment Works sites
GPS Coordinates
NIL
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 200.0M
Total
KES 200.0M
Beneficiaries
20,638
Households
0
Population
Created 16 Aug 2026, 15:51