Ongoing Reticulation sewers Approved

Lot 4 - Construction of East and West of Nairobi Reticulation sewers

Nairobi · Dagoretti North · Kawangware, Kilimani, Kileleshwa,Kabiro,Gatina

Overall Progress
61.80%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Nairobi Rivers Basin Rehabilitation and Restoration Program: Sewerage Improvement Project Phase II
Start Date
03 Sep 2021
Planned End
03 Mar 2023
Actual End
02 Dec 2024
Contractor
China road and Bridge Corporation in JVwith Hubei Shuizong water Resources & Hydropower Construction Co Ltd.
Consultant
Hankuk Engineering Consultanta inJV with Ecosite Development Consultanta Ltd.
Location Type
Urban
Target Areas
Kawangware, Kilimani, Kileleshwa,Kabiro,Gatina
Scope of Works
· Laying of Reticulation sewers
Impacts
Reduce pollution on Nairobi rivers. Restore Nairobi rivers. Contribute to improved health and quality of life through provision of safe and sustainable water and sewerage services.
Key Challenges
delay in issuance of the NEMA Licence and KPC Wayleave clearance to commence Karen Trunk wayleave
Remarks
The bank has yet to issue an update on the contractor's request for an extension of time
GPS Coordinates
1.2890,36.7281
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 12.3M
Adb
🌍 Foreign · Loan
KES 64.6M
Total KES 76.9M
Beneficiaries
600
Households
3,000
Population
Technical Specs
Reticulation Sewer 6.36 km
Created 16 Aug 2026, 15:51 · Last updated 16 Aug 2026, 17:18