Ongoing
Sewer, Water lines and reticulations
Approved
Construction works for Makutano water supply and sewerage projectt
Murang'a · Maragwa · Ichagaki, Kambiti, Wempa, Makuyu, Maragua
Overall Progress
95.52%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Programme
Start Date
09 Oct 2020
Planned End
08 Apr 2022
Actual End
-
Contractor
China Civil Engineering Construction Corporstion Kenya Ltd
Consultant
Losai Management Limited
Location Type
Rural
Target Areas
Kenol, KInyona, Kangari, Mareira , wangu
Scope of Works
48.2 km, OD 200/160 mm transmission main in MUSWASCO area, 123 Km, OD 200-50 mm Last Mile Connectivity pipelines in MWESCO area, 24.3 Km, OD 90 mm Last Mile Connectivity pipelines in GATAWASCO area, 2 No. 250 m3 masonry tanks, INo. Ablution Block at Sabasaba market, 17km of 600/450/300mm dia. DWC trunk sewer pipelines, 15.1km of 250mm dia. DWC pipes of reticulation sewers, Sewage Treatment Plant of capacity 3,000m³/d,1,000 household connections;
Impacts
Access to water supply and improved sanitation services
Key Challenges
Pending payments for sewerlines, deelayed compensation for land at the intake, wayleave
Remarks
There should be regular inspection along the pipelines to identify leakages at early stages. Also there should be increased support to area WSP to be able to address the issue on vandalism.
GPS Coordinates
-0.792407, 37.130656
Funding Sources
Adb
🌍 Foreign
· Loan
KES 924.3M
Total
KES 924.3M
Beneficiaries
17,668
Households
57,252
Population
Technical Specs
Storage Reservoir
250.00 m³
Treated Water Mains
48.74 km
Distribution Lines
148.00 km
Wastewater Treatment Capacity
3,000.00 m³/day
Trunk Sewer Main
17.26 km
Reticulation Sewer
15.46 km
Manholes
634
Non-Sewered Sanitation Facilities
2
Sewer Connections (Households)
1,000