Ongoing Borehole Approved

Borehole drilling and capping for Ainapng'etuny School Water Project

Nandi · Nandi Hills · Kapchorua

Overall Progress
70.00%
Project Overview
Implementing Agency
Lake Victoria North Water Works Development Agency
Programme
Water Harvesting Programme
Start Date
07 Jun 2023
Planned End
07 Aug 2023
Actual End
07 Aug 2023
Contractor
Upwork Enterprises Limited
Consultant
-
Location Type
Rural
Target Areas
Ainapngetung
Scope of Works
Drilling and cappingInstallation of solar power hybrid system, solar flood light, and submersible pump supply and installation of 30m³ elevated structurally pressed steel tank on 10m steel tower rising main from the borehole to elevated tank (500m length) 40mm dia distribution line from the tank chamber (500m long) hdpe 50mm-32mm dia construction of 5nr communal water points
Impacts
Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
Key Challenges
Insufficient budget allocation and late disbursement of project funds which led to delays
Remarks
Project is almost complete
GPS Coordinates
Latitude 0.02186872 Longitude 35.3563612
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 10.0M
Total KES 10.0M
Beneficiaries
375
Households
1,500
Population
Technical Specs
Volume Abstracted 75.60 m³/day
Treatment Capacity 60.48 m³/day
Storage Reservoir 30.00 m³
Treated Water Mains 0.50 km
Distribution Lines 0.50 km
Water Kiosks 5