Ongoing
River Intake
Approved
Mwala Cluster Water Supply and Sanitation Project
Machakos · Mwala · Muthetheni
Overall Progress
55.00%
Project Overview
Implementing Agency
Tanathi Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Start Date
01 Jan 2024
Planned End
12 Jan 2025
Actual End
12 Jan 2025
Contractor
Zhongmei Engineering Group Limited JV Visrom Company Ltd
Consultant
CAS Consultants
Location Type
Rural Urban
Target Areas
Kalimoni
Scope of Works
• Intake weir & Intake works at Munyu River
• Treatment works of 6,600 m3/day
Impacts
The project upon completion will serve the target area with clean, safe, and affordable water
Key Challenges
Slow IPC Payment processes
Remarks
The project ongoing and is within schedule
GPS Coordinates
37.44460, -1.24392
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 235.7M
Adb
🌍 Foreign
· Loan
KES 589.2M
Total
KES 824.9M
Beneficiaries
5,000
Households
25,000
Population
Technical Specs
Volume Abstracted
6,600.00 m³/day
Treatment Capacity
6,600.00 m³/day
Distribution Lines
80.00 km
Water Kiosks
1
Connections
15