Completed
Sanitation
Approved
Othaya Sewerage Project (Last Mile Connectivity Phase I)
Nyeri · Othaya · Mahiga
Overall Progress
100.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Start Date
01 Feb 2019
Planned End
01 Mar 2020
Actual End
-
Contractor
visrom limited
Consultant
-
Location Type
Urban
Target Areas
Othaya Town Environs
Scope of Works
Laying of 7.8 Km Sewer Lines of Diameter 100mm- 225mm
Rehabilitation of an ablution block
Construction of 1No. sludge drying bed
Addendum Works
Kanyange sewerline, Kagonye ablution block, micro-tunneling works
Impacts
Connects Othaya town with reliable sewer system.
Key Challenges
Delays caused by the tax exemption approval process and delay in payment of Advance Payment
Remarks
Improvement of sanitation services within Othaya town
The project is complete and operational
GPS Coordinates
-0.548880000,36.945000000
Funding Sources
Adb
🌍 Foreign
· Loan
KES 78.6M
Total
KES 78.6M
Beneficiaries
600
Households
3,000
Population
Technical Specs
Connections
600
Wastewater Production Capacity
1,100.00 m³/day
Reticulation Sewer
7.80 km
Manholes
156
Sewer Connections (Households)
400