Report Back to Projects
Completed Dam Approved

Thangatha Dam Spillway Repairs

Meru · Tigania East · Thangatha

Overall Progress
100.00%
Project Overview
Implementing Agency
Tana Water Works Development Agency
Programme
Water Harvesting Program
Start Date
-
Planned End
-
Actual End
-
Contractor
AMG Sagirin LTD
Consultant
-
Location Type
Rural
Target Areas
Thangatha
Scope of Works
 Repair of spillway
Impacts
Provision of reliable water for domestic and agricultural use.
Key Challenges
GOK late disbursments
Remarks
Repairs completed, however assessment carried out for remedial works following damage by El Nino floods.
GPS Coordinates
38.166670000,0.083330000
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 3.3M
Total KES 3.3M
Beneficiaries
250
Households
1,250
Population
Technical Specs
Storage Reservoir 20,000.00 m³
Connections 250
Created 16 Aug 2026, 17:18