Report Back to Projects
Completed Springs: Extension of pipeline Approved

Eliye Kaolokol

Turkana · Turkana Central · Kangatotha/ Kalokol

Overall Progress
100.00%
Project Overview
Implementing Agency
North Rift Valley Water Works Developmnet Agency
Programme
GOK Funded Projects
Start Date
04 Oct 2024
Planned End
08 Oct 2024
Actual End
09 Mar 2024
Contractor
Rhumas Co. Ltd
Consultant
-
Location Type
Rural
Target Areas
Eliye, Wadach, Lobolo, Loyolo,.. & Kalokol
Scope of Works
Rehabilitation of intake and laying of 10km water distribution main line
Impacts
Residents accessing better quality water (Non-saline) closer to settlements
Key Challenges
High demand versus low supply, vulnerable infrastructure
Remarks
Phase 1 of the project is complete and operational. Phase 2 undertaken by CRVWWDA for completion of pipeline to Kalokol, 80% complete
GPS Coordinates
3.14'58.32"N 36.01'06.37"E
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 20.0M
Total KES 20.0M
Beneficiaries
2,000
Households
10,000
Population
Technical Specs
Volume Abstracted 100.00 m³/day
Storage Reservoir 150.00 m³
Treated Water Mains 40.00 km
Distribution Lines 15.00 km
Water Kiosks 10
Connections 100