Report Back to Projects
Ongoing Borehole, Water Supply Approved

Mukuru Kwa Reuben-Diamond Village

Nairobi · Embakasi South · Mukuru Kwa Reuben

Overall Progress
1.00%
Project Overview
Implementing Agency
Athi Water Works Development Agency
Programme
Drilling and equipping, solarization and construction of elevated water tanks with Associated distribution networks.
Start Date
-
Planned End
-
Actual End
-
Contractor
Export Hydro Pump and Services (Africa) Limited
Consultant
-
Location Type
Urban
Target Areas
Mukuru Kwa Reuben
Scope of Works
Drilling, Equipping, Elevated tank, Water Kiosks & Associated Piping.
Remarks
Operational
GPS Coordinates
1.3182781,36.8710381
Funding Sources
Gok
🇰🇪 Domestic · Grant
KES 9.0M
Total KES 9.0M
Beneficiaries
1,152
Households
5,760
Population
Technical Specs
Volume Abstracted 288.00 m³/day
Storage Reservoir 24.00 m³
Water Kiosks 1
Created 16 Aug 2026, 17:18
County Overview
Loading…
Loading…

Fetching entity performance details…