Completed
Borehole
Approved
Mbale Rural Health Training Centre
Vihiga · Vihiga · Lugaga-Wamuluma
Overall Progress
100.00%
Project Overview
Implementing Agency
Lake Victoria North Water Works Development Agency
Programme
Universal Health Coverage Program
Start Date
-
Planned End
-
Actual End
-
Contractor
Gari Hills Enterprises
Consultant
-
Location Type
Urban
Target Areas
Mukuli
Scope of Works
Construction of 30m3 Elevated steel tank
Distribution pipeline 500m
Impacts
Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
Key Challenges
Insufficient budget allocation which led to delays and limitations in scope. Late disbursement of project funds
Remarks
It is complete and operationa;l
GPS Coordinates
Latitude 0.07982888
Longitude 34.721078686
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 8.5M
Total
KES 8.5M
Beneficiaries
250
Households
1,000
Population
Technical Specs
Volume Abstracted
68.00 m³/day
Storage Reservoir
30.00 m³
Treated Water Mains
0.10 km
Distribution Lines
0.40 km
Connections
4