Ongoing
Water Supply Project
Approved
Construction of Kabianga Water Supply Project Phase I
Kericho · Belgut · Kabianga, Kibingei and Kapcheluch
Overall Progress
60.00%
Project Overview
Implementing Agency
Lake Victoria South Water Works Development Agency
Programme
GOK Funded Projects
Start Date
-
Planned End
11 Dec 2024
Actual End
04 Nov 2025
Contractor
Smooth Engineering Construction Conmpany Limited
Consultant
-
Location Type
Rural Urban
Target Areas
Kabianga, Kapcheluch and Kibingei Sub-locations
Scope of Works
Construction of 2,000 m3 WTP, Construction of 3 No. water kiosks, Intake works on R. Kabianga, Construction of Raw and Treated water Rising Main, Laying of 9km distribution lines, Construction of 200 m3 elevated storage tank, Electro-mechanical works
Impacts
Improve reliability of safe, treated and reliable water. Reduce waterborne diseases
Key Challenges
Delayed disbursements of funds
Remarks
Project is ongoing with construction of the intake on River Kabianga
GPS Coordinates
738436.93 m E, 9950610.31 m S
Funding Sources
Gok
🇰🇪 Domestic
· Grant
KES 147.0M
Total
KES 147.0M
Beneficiaries
1,500
Households
6,000
Population
Technical Specs
Volume Abstracted
2,200.00 m³/day
Treatment Capacity
2,000.00 m³/day
Storage Reservoir
500.00 m³
Treated Water Mains
2.13 km
Distribution Lines
9.00 km
Water Kiosks
3
Connections
80