Water Supply
Construction of Last Mile for Gachicio Borehole
Kwale · Lunga Lunga · Mwereni
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Contractor
Marsland Construction & General Supplies Ltd
Consultant
—
Start Date
27 Jun 2024
Planned End
28 Sep 2024
Actual End
07 Nov 2024
Scope of Works
Trench excavation and pipelaying 7km | Construction of 1 No CWP
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
600
Households
3,400
Population