Report Back to Projects
Ongoing Water Supply

Construction of Last Mile for Gachicio Borehole

Kwale · Lunga Lunga · Mwereni

Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Rehabilitation of Water Supply
Contractor
Marsland Construction & General Supplies Ltd
Consultant
Start Date
27 Jun 2024
Planned End
28 Sep 2024
Actual End
07 Nov 2024
Scope of Works
Trench excavation and pipelaying 7km | Construction of 1 No CWP
Impacts
Improve access to water
Key Challenges
No challenges
Funding Sources

No funding sources recorded.

Total KES 0.0M
Beneficiaries
600
Households
3,400
Population