Ongoing
Sewerage System
Narok Town Sewerage Project
Mombasa · Jomvu · Mikindani
Overall Progress
100.00%
Project Overview
Implementing Agency
Central Rift Valley Water Works Development Agency
Programme
Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Contractor
Sinohydro Corporation Ltd
Consultant
Mangat IB Patel
Start Date
15 Apr 2019
Planned End
12 Jan 2021
Actual End
12 Jan 2021
Scope of Works
Construction of RE’s Office; Secondary Sewers –length of 26.1km-; Trunk Sewers of 14.2 Km,,Main Trunk Sewers of 11Km,Sewage Treatment Works (3,000m3 Capacity)Last Mile Connectivity Works 81kms of pipe dia 50, 75, 110 and 160mm & 169Nr Concrete Valve chambers 2400 water connections and 500 sewer connections
Impacts
Improve access to water
Key Challenges
No challanges
Funding Sources
No funding sources recorded.
Total
KES 0.0M
Beneficiaries
21,900
Households
109,500
Population